We consolidated four legal entities into one
and converted Actual Cost to Standard Cost.

While complying with global headquarters' guidelines, we standardized disparate processes and master data onto a single set of standards.

INDUSTRY
Manufacturing · Door Locks & Access Hardware
SIZE
SMB
YEAR
2017 · 2023
SOLUTION
AX2012
CUSTOMER

Customer

ASSA ABLOY is a global access solutions company headquartered in Sweden, and a world leader in door locks and access hardware. In Korea, it manufactures and supplies products through a number of affiliated companies.
BACKGROUND

Background

The challenge was to bring systems built separately for each affiliate together into a single legal-entity structure.

01

Consolidate AX2012 instances implemented separately across 4 affiliates into a single Legal Entity

02

Needed a Cost Conversion from Actual Cost to Standard Cost

03

Required compliance with guidelines requested by Global HQ

SCOPE

Modules Implemented

We reorganized company-wide modules around the consolidated standard, and carried out the Standard Cost conversion as a separate workstream.

OPERATION

Sales · Production · Logistics

  • Master Data · Sales · Procurement · Materials
  • Inventory · Logistics · Production
FINANCE

Finance · Management Accounting

  • Financial Accounting · Treasury · Management Accounting
  • Budget · Fixed Assets · Period-End Close
CONVERSION

Standard Cost Conversion

  • Standard Cost Conversion
  • New Profit Center Dimension Design
  • BOM · Route · Rate Adjustments
RESULTS

Results

CONSOLIDATION

Consolidation of 4 Legal Entities

To consolidate 4 Legal Entities into one, we standardized disparate processes and master data.

REPORTING

Preserved Entity-Level P&L Reporting

To preserve profit-and-loss calculation by the original Legal Entities, we added a new Profit Center Dimension and reflected it in the financial statement design.

COST

Standard Cost Conversion

We used Conversion Simulation to analyze Cost Variance Impact in advance, secured data integrity through BOM, Route, and rate adjustments, then reflected the standard cost data in the system.

COMPLIANCE

Compliance With Global Guidelines

We completed the project while complying with the guideline requirements requested by Global HQ.